Power failure outsourcing construction safety locking procedures
Outsourcing units by workshop maintenance guardian led to the mechanical and electrical workshop for power cut tickets and access to the collective lock lock. After locking, the key shall be kept by the maintenance person in charge of the outsourcing unit.
Outsourcing construction safety unlocking procedures
1. After the inspection and maintenance work is finished, the person in charge of inspection and maintenance of the outsourcing and the guardian of the workshop shall check the maintenance site, confirm that all the maintenance personnel are removed from the maintenance site, and the safety measures for maintenance shall be restored. The person in charge of inspection and maintenance of the outsourcing and the guardian of the workshop shall take the collective keys and blackout tickets to the electromechanical workshop to handle the transmission tickets.
(2) the electrical operator, the workshop guardian, the person in charge of external maintenance must carry out a careful inspection of the maintenance site, confirm that there is no hidden danger in the maintenance site, all safety protection facilities have been restored, in line with the unlocking conditions after the three parties arrived at the maintenance equipment isolation point after the joint unlock.
(3) after the completion of unlocking by the electrical operator delisting power.
Work stoppage, transfer procedure
1. In the same job gap in maintenance project, the maintenance personnel should withdraw from work site, all security measures to keep still, still by the maintenance charge of deposit and keep it locked all the safety lock, discontinuous, continue to work, maintenance must confirm, head of the personal lock box in good condition, no loss and collective lock key confirmed rear can carry out normal operation site safety measures.
2. The same maintenance projects need to transition to continue work on duty, head of the maintenance working ticket must be handed over to the maintenance work, check the number and the collective lock handover, maintenance staff on duty when confirmed superior personal lock, maintenance staff work to remove personal lock, and to make a good record of succession rear can begin to repair.